Preliminary Run Update

Here is a break down of what is currently taking place at the manufacturer during the preliminary run:

The tooling is mechanically hoisted up by a trollie crane and secured to the machine by several dozen very large bolts. This process alone takes a couple hours for each mold (the stock kit consists of six molds).

Our molder works to tweak the factory provided set points for the temperature of the molds and the cycling intervals for optimum quality.

There are also two parts which will require jigs to be sure the form is not warped after coming off the line.

They felt confident that by the end of this week they would be able to have the preliminary runs completed.